Over-or under applied overhead


Schlamber Company Factory overhead rate is Rs.2 per hour. Budgeted overhead for 3,000 hours per month is Rs. 8,000 and 7,000 hours is Rs. 12,000. Actual factory overhead for the month was Rs.9, 000 and actual volume was 5,000 hours.

Required:

1. Applied overhead

2. Over-or under applied overhead.