One common way to compute the estimate to completion etc is


One common way to compute the estimate to completion (ETC) is to add the budget at completion (BAC) and the value already earned, and

If AC = 900, PV = 800, SPI = 0.90, and the project was supposed to be 40% done by now, what is the current EAC assuming performance will not change for the rest of the project?