On march 1 felt co began construction of a small building


On March 1, Felt Co. began construction of a small building. Payments of $120,000 were made monthly for three months beginning March 1. The building was completed and ready for occupancy on June 1. In determining the amount of interest cost to be capitalized, the weighted-average accumulated expenditures are

a.   $30,000.

b.   $60,000.

c.   $120,000.

d.   $240,000.