Olin transmissions inc has the following estimates for its


Question: Olin Transmissions, Inc., has the following estimates for its new gear assembly project: price = $147 per unit; variable costs = $32 per unit; fixed costs = $41788; quantity = 7413 units. Suppose the company believes all of its estimates are accurate only within +/-15 percent. What is the company's EBIT when it performs its best-case scenario analysis? (Round your final answer to the nearest dollar amount. Omit the "tiny_mce_markerquot; sign and commas in your response. For example, $123,456.78 should be entered as 123457.)