Number of communication channels


Complete the mcq:

1. If a project has 12 stakeholders what is the total number of communication channels?

10

45

66

24

2. The goal of controlling communications is to share information regarding the project's with performance stakeholders and to improve upon the established?

Communication process

Stakeholder management plan

Project planning process

Statement of work

3. The receiver confirms that the message is being received through feedback question is called?

Encoder messaging

Feedback

Medium

Active listening

4. The pitch, tone, and inflections in the sender's voice affecting the message being sent is known as?

Paralingual

Decoder

Active listening

Receiver

5. The communication approach pulls the information from a central repository like a database of information. The approach is good for a large number of stakeholders who want to access information?

Push

Pull

Status review meeting

Medium

6. The five inputs to a risk management plan include project management plan, charter, stakeholder register, enterprise environmental factors, and ______________?

Scope document

WBS

Organizational process assets

Probability charts and timetables

7. Risk identification involves a systematic process of moving through the project, the project plan, the WBS, and supporting documents to identify all possible risk. Two categories of risk reflect all risk. The two are pure risks and ?

Business risks

Scope risks

Resource risks

Schedule risks

8. Qualitative risk analysis is often the first pass in evaluating risk. Qualitative risk analysis helps prioritize risks based on probability of occurrence and impact on project. Qualitative risk analysis attempts to?

Qualify risks

Assess risks against company resources

Evaluate risks in terms of timing within project

Determine when risks may occur


9. As risk analysis happens throughout the project, one of the documents that is always updated as new risks are identified and known risks re-evaluated is the?

Risk matrix

Risk management plan

Risk register

Risk score card

10. An example of a response to risk is avoidance. One way to avoid the risk is to?

Shut down project

Accept the risk

Buy insurance to offset risk if it occurs

Ignore the risk