Assignment:
Tej Dhakar’s company wants to establish kanbans to feed a newly established work cell. The following data have been provided. How many kanbans are needed?
| Daily demand |
250 units |
| Lead time |
1/2 days |
| Safety stock |
1/4 days |
| Kanban size |
50 units |
Provide complete and step by step solution for the question and show calculations and use formulas.