Network diagramming activity predecessor duration a start 2


Network Diagramming Activity Predecessor Duration A START 2 B A 5 C A 6 D B 9 E B, C 3 F D, E 4 What are the paths? What is the critical path? What is the near critical path? Which activities have float? How much?