Network diagram and identifying the path


Question: Given the information in the following table

Activity Duration Predecessor
a 4 None
b 6 a
c 4 a
d 2 c
e 4 b
f 5 b, d
g 3 c
h 4 f,g
i 2 e, h

a. Construct the network diagram

b. Identify each activity's EST, EFT, LST adn LFT

c. Identify all paths. Which path is the critical path?

d. Calculate the slack each activity?

e. How long will it take to complete the project?

Solution Preview :

Prepared by a verified Expert
Project Management: Network diagram and identifying the path
Reference No:- TGS01954469

Now Priced at $25 (50% Discount)

Recommended (97%)

Rated (4.9/5)