Neeras task was supposed to take 2 days and complete on


A) Neera's task was supposed to take 2 days and complete on Tuesday. On Wednesday one of Neera's co-workers asks if she is done, and she says not yet, but she will be done on Thursday. The co-worker finds this alarming and brings it to the attention of the Project Manager, who says she is not worried about that task yet. Of the following choices, which would be the best reason for the Project Manager's lack of concern?

Select one: a. Neera's task has 2 days of lag b. Neera's task has 2 days of float c. Neera's task has 6 days of float d. Neera's task is not on the critical path

B) During project execution, a stakeholder expresses a concern that you will be able to effectively manage to achieve the project's objectives. To address her concern, the document that would be best to show her would be:

Select one: a. The Scope Management Plan b. The Scope Statement c. The Project Management Plan d. The Charter

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Neeras task was supposed to take 2 days and complete on
Reference No:- TGS02537005

Expected delivery within 24 Hours