what is the critical path for this project and how


The following is the activity and associated costs for the renovation of the local high school football stadium. The times are in weeks.

Activity

Immediate Predecessor

Time

Cost ($)

A

-

4

25,000

B

-

5

30,000

C

A

3

15,000

D

B

8

50,000

E

B

2

12,000

F

C, D

3

15,000

G

C, D

7

46,000

H

E, F

2

20,000

 1. What is the critical path for this project?

 2. How much of the total budget would be spent in Week 8 (Period 8) with the earliest start budget?

Request for Solution File

Ask an Expert for Answer!!
Advanced Statistics: what is the critical path for this project and how
Reference No:- TGS0660195

Expected delivery within 24 Hours