Sud and Duds laundry washed and pressed the following number of dress shirts per week.
week work crew total hours shirts
1 sud and dud 24 68
2 sud and dud 46 130
3 sud, dud, and jud 62 152
4 sud, dud and jud 51 125
5 dud and jud 45 131
a. Determine the labor productivity radio for each week.