Problem: In the following MRP planning schedule for item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week.
|
Item J
|
0
|
1
|
2
|
3
|
4
|
5
|
|
Gross requirements
|
|
|
75
|
|
50
|
70
|
|
On-hand
|
|
|
40
|
|
|
|
|
Net requirements
|
|
|
|
|
|
|
|
Planned order receipt
|
|
|
|
|
|
|
|
Planned order release
|
|
|
|
|
|
|