Mre80002 dredging engineering 2016 assignment your task is


Dredging Engineering Assignment

To ensure safe access to the Port of Geelong, maintenance dredging is needed in the South Channel (see Figure 1). The operation will remove a layer of sediment of approximately 0.45m: the first 0.2m of this layer is a highly polluted mud; the remaining 0.25m is sand. The length of the channel requiring maintenance is approximately 3000m; the channel width is 200m.

A possible dumping ground for the sand is suggested in the figure. However, this is not suitable for the mud. An alternative solution for the disposal of mud has to be sought.

Your task is to provide a detailed management plan for this operation. The plan should include, but not necessarily be limited to, Project background & Objectives, Project safety, Environmental issues (Policies, Controls, Impacts, etc...), Dredging Program (be as specific as possible, include dredging requirements, equipment, dredge plume impacts etc), Monitoring/Surveying, Disposal of dredged material, Risks and Contingency Plans. If needed, you can refer to assignment 1 for plume dispersion.

267_figure.png

Request for Solution File

Ask an Expert for Answer!!
Other Engineering: Mre80002 dredging engineering 2016 assignment your task is
Reference No:- TGS01397600

Expected delivery within 24 Hours