An NC drill press drills four 10.0-mm diameter holes at four locations on a flat aluminum plate in a production work cycle. Although the plate is only 12 mm thick, the drill must travel a full 20 nun vertically at each hole location to allow for clearance above the plate and breakthrough of the drill on the underside of the plate. Cutting conditions: speed = 0.4 m/sec and feed = 0.10 mm/rev. Hole locations are indicated in the following table:

Hole Number

x-coordinate (mm)

y-coordinate (mm)

1

25.0

25.0

2

25.0

100.0

3

100.0

100.0

4

100.0

26.0

The drill starts out at point (0,0) and returns to the same position after the work cycle is completed. Travel rate of the table in moving from one coordinate position to another is 500 mm/min. Owing to effects of acceleration and deceleration and the time required for the control system to achieve final positioning, a time loss of 3 sec is experienced at each stop-ping position of the table. Assume that all moves are made to minimize the total cycle time. If loading and unloading the plate take 20 sec (total handling time), determine the time required for the work cycle.

 

Provide complete and step by step solution for the question and show calculations and use formulas.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Minimizing the total cycle time
Reference No:- TGS01977992

Expected delivery within 24 Hours