A construction site needs to move quantities of fill from 4 bunkers to 7 sites. The table describes the move distances between points and the quantities available and those required. Evaluate the moves that reduce the distance times volume moved to accomplish the plan.
| Qty Needed |
Distance from Fill Bunkers to sites (miles) |
| Site |
(cubic ft) |
A |
B |
C |
D |
| 1 |
247 |
26 |
28 |
20 |
26 |
| 2 |
394 |
12 |
14 |
26 |
10 |
| 3 |
265 |
10 |
12 |
20 |
4 |
| 4 |
105 |
18 |
20 |
2 |
16 |
| 5 |
90 |
11 |
13 |
6 |
24 |
| 6 |
85 |
8 |
10 |
22 |
14 |
| 7 |
145 |
20 |
22 |
18 |
21 |