Mill billed and collected 3000000 from drew in 1996 what


Question - Mill Construction Co. uses the percentage-of-completion method of accounting. During 1996, Mill contracted to build an apartment complex for Drew for $20,000,000. Mill estimated that total costs would amount to $16,000,000 over the period of construction. In connection with this contract, Mill incurred $2,000,000 of construction costs during 1996. Mill billed and collected $3,000,000 from Drew in 1996. What amount should Mill recognize as gross profit for 1996?

a. $250,000

b. $375,000

c .$500,000

d. $600,000

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Mill billed and collected 3000000 from drew in 1996 what
Reference No:- TGS02600275

Now Priced at $25 (50% Discount)

Recommended (93%)

Rated (4.5/5)