Material purchase price variance-material quantity variance


Esther Industries developed the following standards for one of its products:

Material                     6 feet      $15/foot     $90
Labor                      10 hours    $12/hour    120

Total variable cost    $210

Actual results for September were:

Units produced    13,000
Material purchased    40,000 feet for $14.25/foot
Material used    80,000 feet
Direct Labor    127,500 hours at $12.25/hour

Required:

(1.) Calculate the following variances

(a.) Material purchase price variance
(b.) Material quantity variance
(c.) Labor rate variance
(d.) Labor efficiency variance

(2.) Why would it be inappropriate to calculate the Material price variance at the time the material is used; might there be a situation when it might be all right to do so?

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Material purchase price variance-material quantity variance
Reference No:- TGS01738589

Now Priced at $20 (50% Discount)

Recommended (97%)

Rated (4.9/5)