Manufacturing overhead is allocated to products based on the number of machine hours required. In a year when 20,000 machine hours were anticipated, costs were budgeted at $125,000. If a product requires 7,000 machine hours, how much manufacturing overhead will be allocated to this product?

A) $41,667

B) $43,750

C) $1,120

D) $50,000