Managers at wagner fabricating company are reviewing the


Managers at Wagner Fabricating Company are reviewing the economic feasibility of manufacturing a part that the company currently purchases from a supplier. Forecasted annual demand for the part is 3,200 units. Wagner operates 250 days a year.

Wagner’s financial analysis established a cost of Capital of 14% for the use of funds for investments within the company. In addition, over the past year $6000,000 was the average investment in the company’s inventory. Accounting information shows that a total of $24,000 was spent on taxes and insurance related to the company’s inventory. In addition, an estimated $9,000 was lost due to inventory shrinkage, which included damaged goods as well as pilferage. A remaining $15,000 was spent on warehouse overhead, including utility expenses for heating and lighting.

An analysis of the purchasing operation shows that approximately two (2) hours are required to process and coordinate an order for the part regardless of the quantity ordered. Purchasing salaries average $28 per hour, including employee benefits. In addition, a detailed analysis of 125 orders showed that $2,375 was spent on telephone, paper, and postage directly related to the ordering process.

A one-week lead time is required to obtain the part from the supplier. An analysis of demand during the lead time shows it is approximately normally distributed with a mean of 64 units and a standard deviation of 10 units. Service level guidelines indicate that one stock-out per year is acceptable.

Currently, the company has a contract to purchase the part from a supplier at a cost of $18 per unit. However, over the past few months, the company’s production capacity has been expanded. As a result, excess capacity is now available in certain production departments, and the company is considering the alternative of producing the parts itself.

Forecasted utilization of equipment shows that production capacity will be available for the part being considered. The production capacity is available at the rate of 1,000 units per month, with up to five months of production time available. Management believes that with a two-week lead time, schedules can be arranged so that the part can be produced whenever needed. The demand during the two-week lead time is approximately normally distributed with a mean of 128 units and a standard deviation of 20 units. Production costs are expected to be $17 per part.

A concern of management is that setup costs will be significant. The total cost of labor and lost production time is estimated to be $50 per hour, and a full eight-hour shift will be needed to setup the equipment for producing the part.

What recommendations can I give in a report format?

Request for Solution File

Ask an Expert for Answer!!
Financial Management: Managers at wagner fabricating company are reviewing the
Reference No:- TGS02686002

Expected delivery within 24 Hours