Make your heading titled process flow diagram make your


Course Textbook

Godish, T., Davis, W. T., & Fu, J. S. (2015). Air quality (5th ed.). Boca Raton, FL: CRC Press.

Our course project will be to develop a document titled A Permit By Rule (PBR) Application for an Interior Surface Coating Facility that will serve as a simulation of our work as a contract environmental engineer to a small vehicle body shop located in the state of Texas.

The Scenario:

You have been contracted with a vehicle body repair shop named Texas Car Body Repairs, USA to engineer and write a state (Texas) air permit application for a carefully designed interior lining (painting) facility. According to Texas state laws and EPA laws, the facility must have an air permit before construction begins. Once the facility is completed, the construction air permit will then become the operational air permit for the facility. As a result, your client wants the air permit application to automatically align the interior surface coating facility into operational compliance with state and federal air quality laws. Consequently, it is extremely important for you to write the air permit application to meet the air permit criteria using the state guidance document and considering the equipment and chemicals already planned for the facility operations.

Your client has presented you with the following specifications regarding the facility operations plan:

Interior Liner Coating Material

10 gallons coating/vehicle

2 gallons of solvent/vehicle

Vehicle Lining Application

Apply interior liners to two (2) vehicles/day

Work five (5) hours/day and four (4) days/week Vehicle Lining Curing

Vehicle Lining Curing

Cure interior liners of two (2) vehicles/day

Work five (5) hours/day and four (4) days/week

Interior Liner Cure

Heater fuel source is natural gas-fired drying oven

Heater generates 2.1 million (MM) Btu/hr at maximum 2,500 hrs/year

Vehicle Lining Design

Cross-draft air plenum

Vehicle interior is the spray area

Exhaust Fan

10,000 ft3/min (CFM)

1 exhaust fan

Air Makeup Unit

5760 ft3/min (CFM)

1 air makeup

Filter Openings

20.0 ft2 each

Two (2) filter openings

Coating WV

VOC content

2.8 lb/gal coating Coating VM

Water Content

Per gal/coating

1.0 lb/gal

Water Density

Per gal/water

8.34 lb/gal

Coating VW

Water volume

Calculation

Exempt-solvent Content

Per gal/coating

0.5 lb/gal

Exempt-solvent Density

Per gal/exempt solvent

6.64 lb/gal

Coating Ves

Exempt solvent volume

Calculation

The client has designed an interior coating spray painting system that allows the interior of a vehicle to be coated (such as for new vehicles, or vehicles being restored after fire damage or other catastrophic interior damage). The operations will involve a stripped-down vehicle body being brought into the facility's shop. The shop is a steel building with a finished concrete floor and a paint booth for each vehicle. The vehicle will be placed in the spray booth. The booth will be opened at one end of the booth for makeup air. The exhaust air will flow through an exhaust chamber at the other end of the vehicle (see Cross-Draft Automotive Spray Booth in Appendix F of the TCEQ Regulatory Guidance Document). For each vehicle, once the liner application operations are completed the forced curing (drying) operations will immediately commence.

Instructions:

A Permit By Rule (PBR) Application for an Interior Surface Coating Facility, complete the final two sections, "Pollution Control Technologies" and "Process Flow Diagram" of your proposal by following the instructions carefully, and then submit the completed, final draft of your proposal for grading.

1. Closely read the Required Reading assignment from your textbook, the TCEQ (2011) document, and the Unit Lesson in the Study Guide.

2. Consider the control technology options available for our scenario.

Make your first Unit VIII section your seventh level 1 heading titled "Pollution Control Technologies." Select appropriate control technologies to be used in the final exhaust air from the spray booth for the following pollutants: (a) gases and vapors, (b) aerosol particles, and (c) noise levels of 90 dBA at 1,000 Hz. Be sure to defend your suggested engineering controls with literature.

3. Make your second Unit VIII section your eighth (final) level 1 heading titled "Process Flow Diagram." Map out the entire process by developing a drawing of the process. You might consider reviewing the drawings located within Appendix G and Appendix J in the TCEQ (2011) document and Figure 10.12 on page 381 of your textbook as good examples of clear and understandable process drawings to help you construct your own Process Flow Diagram.

4. Be sure that your Abstract and References pages are included.

Solution Preview :

Prepared by a verified Expert
Dissertation: Make your heading titled process flow diagram make your
Reference No:- TGS01410111

Now Priced at $35 (50% Discount)

Recommended (99%)

Rated (4.3/5)