Make the entry to record construction costs of 3600000 on


Question - Sherman Construction Company was awarded a contract to construct an interchange at the junction of U.S. 66 and Highway 40 at a total contract price of $8,000,000. The estimated total costs to complete the project were $6,000,000.

Instructions

a. Make the entry to record construction costs of $3,600,000, on construction in process to date.

b. Make the entry to record progress billings of $2,000,000.

c. Make the entry to recognize the profit that can be recognized to date, on a percentage-of-completion basis.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Make the entry to record construction costs of 3600000 on