Make a job order cost sheet


The Talbott Company has received an order (#324) for 100 widgets. On January 20 the shop supervisor requisitioned 100 units of part 503 at a cost of $5 per unit and 500 units part 456 at a cost of $3 per unit to begin work on the 100 widgets. On the same day 20 hours of direct labor at $20 per hour are used to work on the widgets. On January 21, 200 units of part 543 at $6 per unit are requisitioned and 10 hours of direct labor at $15 per hour are performed on the 100 units of widgets to complete the job. Overhead is allocated to the job based on $5 per direct labor hour. Make a job order cost sheet for the 100 widgets.