Machine a has a projected average operating time of 150


A manager must decide between two machines. The manager will take into account each machine's operating costs and initial costs, and its breakdown and repair times. Machine A has a projected average operating time of 150 hours and a projected average repair time of 5 hours. Projected times for machine B are an average operating time of 58 hours and a repair time of 6 hours. What are the projected availabilities of each machine?

Solution Preview :

Prepared by a verified Expert
Business Management: Machine a has a projected average operating time of 150
Reference No:- TGS01610009

Now Priced at $10 (50% Discount)

Recommended (97%)

Rated (4.9/5)