List the nodes in the order of traversal in the critical


NEED HELP DRAWING A PERT CHART

1. Using the information that follows in the table below, including the related question sets, please draw the PERT chart for the first half of this course - from [and including] the first lecture through to the end of the Midterm .

CLASS       DATE                LECTURE TOPIC

1              - SEP 12 -             Introduction to Project Management & WBS Assignment Issued

2              - SEP 19 -            PMBOK - Project Management Framework

3              - SEP 26 -            PMBOK - Lifecycle and Organization + WBS Assignment "First Draft" Deadline

4              - OCT 03 -            PMBOK - Project Management Processes

5              - OCT 10 -            PMBOK - Scope, Cost, Quality and Risk Management + WBS "Final Draft" Deadline

6              - OCT 17 -            Mid-Term [in class]

The recommended model for your chart is the one depicted in the netmba.com document as follows:

1939_Chart.jpg

2. How many critical paths should there be in your PERT chart? Explain your answer.

3. List the nodes [in the order of traversal] in the critical path[s] that you have identified in question 6 [above] and documented in your PERT chart.

40 t=3wk t=1wk t=3wk t=2wk 10 D >150 t=4wk t=2wk 30 NetMBA.