Lead time for tires is 6 days with daily demand of 100


Lead time for tires is 6 days with daily demand of 100 tires and a safety stock of 3 days. Each container (kanban) holds 10 tires.

What is the correct number of kanbans?

The number of kanbans required is equivalent to the ratio of what two valules (in words)?

Please show work.