Last year 15000 customer orders at the mill and the manager


A standard work year is 2080 hours at luther mill and it takes about 2 hours to fill a customer order. The manager is always concerned about employee idle time, so he aims for a capacity cushion of two percent. Last year 15000 customer orders at the mill and the manager has a new Mercedes in mind as a company car, so he hopes that there is an increase of 10% in customer orders for the next year. How many workers will the manager need to have at the mill next year.

Solution Preview :

Prepared by a verified Expert
Mathematics: Last year 15000 customer orders at the mill and the manager
Reference No:- TGS01628045

Now Priced at $20 (50% Discount)

Recommended (93%)

Rated (4.5/5)