Large industrial compressor


Manceville Air has just produced the first unit of a large industrial compressor that incorpotated new technology in the control circuts and a new internal venting system. The first unit took 108 hours of labor to manufacture. The company knows from past experience that this labor content will decrese significantly as more units are produced. In reviewing past production data, it appears that the company has experienced a 80% learning curve when producing similar designs.

Your job as the production cost estimater is to prepre the estimate

Total manufacturing time for the

First 8 units is 577 hours

Manufacturing time for the last 7 units =_____hours (i.e, units 2 thru 8)