Labour rate variance


Borden Enterprises uses standard costing. For the month of April, the company reported the following data: Standard direct labour rate $10 per hour Standard hours allowed for actual production 8,000 Actual direct labour rate $9.50 per hour Labour efficiency variance $4,800 favourable What was the labour rate variance for April?

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Labour rate variance
Reference No:- TGS038426

Expected delivery within 24 Hours