Jre2 inc entered into a contract to install a pipeline for


JRE2 Inc. entered into a contract to install a pipeline for a fixed price of $2,350,000. JRE2 recognizes revenue upon contract completion.


Cost incurred

Estimated Cost to Complete

2015

$ 270,000

$ 1,650,000

2016

1,700,000

600,000

2017

550,000

0

In 2016, JRE2 would report gross profit (loss) of:

a. $(270,000).

b. $(390,000).

c. $0.

d. $(220,000).

 