Job number 5-23 had 500 hours of direct labor what is the


A manufacturing company allocates overhead at a fixed rate of $50 per hour based on direct labor hours. During the month, total overhead incurred was $280,000, and the total direct labor hours work was 4,000. Job number 5-23 had 500 hours of direct labor. What is the amount of overhead allocated to job 5-23?

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Job number 5-23 had 500 hours of direct labor what is the