Job-cost records for bodhi company contained the following


Question - Job-cost records for Bodhi Company contained the following data:

Job No.

Date Started

Date Finished

Date Sold

Total Cost of Job at June 30

220

May 18

June 12

June 20

$6,000

221

May 20

June 9

June 21

4,000

222

June 7

July 5

July 12

7,000

223

June 10

July 28

July 1

6,500

224

June 19

July 16

July 25

8,000

Required:

a. Compute WIP inventory at June 30.

b. Compute finished goods inventory at June 30.

c. Compute cost of goods sold for June.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Job-cost records for bodhi company contained the following
Reference No:- TGS02858854

Now Priced at $25 (50% Discount)

Recommended (92%)