Job 3 will take seven on a and three on b job 4 will take


A machine shop has two machines, A and B. Four jobs need to be processed through machine A first and B second. Job 1 will take one hour on machine A and three hours on machine B. Job 2 will take three hours on A and two hours on B. Job 3 will take seven on A and three on B. Job 4 will take five hours on A and one hour on B. Using Johnson’s rule, in what order should these jobs be done?

Solution Preview :

Prepared by a verified Expert
Finance Basics: Job 3 will take seven on a and three on b job 4 will take
Reference No:- TGS01524619

Now Priced at $10 (50% Discount)

Recommended (97%)

Rated (4.9/5)