Jessica just received the following information on her


Jessica just received the following information on her project: PV = 200, EV = 300, AC = 250, BAC = 1500, EAC = 1208. In terms of cost at completion. The project will currently finish under budget. The project will currently finish over budget. The project will currently finish on budget. The project will currently finish behind schedule. There is insufficient information to draw conclusions.