It has been estimated that a minimum run off of


It has been estimated that a minimum run off of approximately 94 m3/sec will be available at a hydraulic project with a head of 39 m. Determine

(i) firm capacity

(ii) yearly gross output.

Assume the efficiency of the plant to be 80%.