It expects the project will be completed on time and on


Question - Essetle Constructions has a contract to build a train network for a price of $12 million. The project is expected to take three years to complete and to cost $8 million. Essetle spent $2.5 million in the first year and $4 million in the second year. It expects the project will be completed on time and on budget. How much profit should Essetle Construction report for the second year of the contract?

a. $1 Million

b. $2 Million

c. $4 Million

d. $6 Million

e. No Profit should be reported

Solution Preview :

Prepared by a verified Expert
Accounting Basics: It expects the project will be completed on time and on
Reference No:- TGS02814560

Now Priced at $20 (50% Discount)

Recommended (98%)

Rated (4.3/5)