Indicate the es earliest start ef earliest finish ls latest


Task

Predecessors

Duration (weeks)

A

-

3

B

-

4

C

A

2

D

C

5

E

B

7

F

D,E

1

G

D

4

H

F,G

5

Draw an AOA (Activity on Arrow) diagram of the project.

(b) Indicate the ES (Earliest Start), EF (Earliest Finish), LS (Latest Start), LF (Latest Finish) times for each of the activities A through H.

(c) Tabulate the slacks of the tasks.

(d) What is the critical path(s)?

(e) How many weeks does it take to complete the project according to the critical path analysis?