Indicate the critical path activities and what is the


2334_Calculate the project completion time.png

 

Activity

Mean duration

Std. dev. (days)

A

11

0.9

B

13

1.1

C

7

0.2

D

9

0.8

E

6

1

F

7

1.2

G

10

0.7

H

9

0.6

I

8

0.8

Complete the following:

  1. Calculate the project completion time.
  2. Indicate the critical path activities.
  3. What is the probability of completing this project between 38 and 40 days?
  4. What are the slack values for activities C and F? Interpret the meaning of their slack values?