Inconsistency in the ranking of the two projects


Problem:

A company is considering which of two mutually exclusive projects it should undertake. The Finance Director thinks that the project with the higher NPV should be chosen whereas the Managing Director thinks that the one with the higher IRR should be undertaken especially as both projects have the same initial outlay and length of life. The company anticipates a cost of capital of 10% and the net after tax cash flow of the projects are as follow:

Year (Cash Flow 000's )    0        1       2      3       4       5
Project X                     (200)     35      80    90     75     20
Project Y                     (200)    218      10    10      4       3

Required to do::

a) Calculate the NPV and IRR of each project.

b) State with reasons, which project you would recommend.

c) Explain the inconsistency in the ranking of the two projects.

Solution Preview :

Prepared by a verified Expert
Finance Basics: Inconsistency in the ranking of the two projects
Reference No:- TGS02047610

Now Priced at $20 (50% Discount)

Recommended (98%)

Rated (4.3/5)