In the following table the activities with their precedence


In the following table the activities with their precedence sequence and expected time? (days) are listed for a? project:

Activity Immediate Predecessor(s) Time (days)

A - 7

B A 2

C A 4

D B 5

E B 5

F C 5

G E, F 2

H D 3

I G, H 5

a) The activities on the critical path are

b) The project length is