In october roby company reports 19990 actual direct labor


Question - In October, Roby Company reports 19,990 actual direct labor hours, and it incurs $236,226 of manufacturing overhead costs. Standard hours allowed for the work done is 25,020 hours. The predetermined overhead rate is $9.65 per direct labor hour. In addition, the flexible manufacturing overhead budget shows that budgeted costs are $7.82 variable per direct labor hour and $43,950 fixed.

Compute the overhead controllable variance.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: In october roby company reports 19990 actual direct labor
Reference No:- TGS02428933

Now Priced at $25 (50% Discount)

Recommended (91%)