Jack Sampson, contracted negation for Nebula Airframe Company, is currently involved in bidding on a follow-up government contract. In gathering cost data from the first three units, which nebula produced a research and development contract, he found that the first unit took 2,000 labor hors, the second took 1,800 labor hours, and the third took 1692 hours. In contract for three more units, how many labors hours should Simpson plan for?