In case of a tie use the tiebreaker of assigning the task


Questions : Management at Fullerton Media wants to design an assembly line that will turn out 800 videotapes per day. There will be 8 working hours in each day.

The industrial engineering staff has assembled the info below:

Task Immediate Predecessor Time (min.)
a - 0.2
b a 0.2
c - 0.4
d - 0.1
e c,d 0.3
f b,e 0.2
g - 0.1
h f,g 0.2
i h 0.5

1.What is the maximum cycle time? _____min (use 1 decimal place)

2.What is the minimum cycle time? _____min (use 1 decimal place)

3. Determine the appropriate cycle time based on the demand. _____min (use 1 decimal place)

4. What is the minimum number of stations possible? _____ workstations (the answer is an integer value)

5. Assign tasks to workstations using this rule: Assign tasks according to the greatest number of following tasks.

In case of a tie, use the tiebreaker of assigning the task with the longest processing time first. What is the efficiency of the line? _____ % (Use 1 decimal place, e.g. 12.3%, but type in only the number, e.g. 12.3, without the percentage symbol)