In calculating the risk associated with two potential


In calculating the risk associated with two potential projects (A & B), which of the following statistical calculations indicates that the projects are equally risky?

i. The standard deviation of A is 100, and the coefficient of variation of A is 80.912

ii. The standard deviation of B is 1,000, and the coefficient of variation of B is 809.12

iii. The variance of A’s possible outcomes is 258.10, and the standard deviation of A is 100

iv. The variance of B’s possible outcomes is 2,581, and the standard deviation of B is 1,000

a) iii and iv

b) ii and iii

c) i and ii

d) i and iv

e) None of the above

Request for Solution File

Ask an Expert for Answer!!
Financial Management: In calculating the risk associated with two potential
Reference No:- TGS01423727

Expected delivery within 24 Hours