In a public construction contract between state 0 and


In a public construction contract between state "0" and contractor "C", the contract stated that the unit price for rock excavation will apply to all rock removed above or below these quantities. C was required to include 1,000 cubic yards of rock excavation in its basic bid. C actually excavated 3,000 cubic yards and was delayed 6 months to complete the excavation. C inspected the project site as required in O's bidding documents and observed nothing to indicate any excess above 1,000 cubic yards, C was not required under the Contract to perform its own subsurface study. C seeks delay damages. What result? Explain.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: In a public construction contract between state 0 and
Reference No:- TGS01512821

Expected delivery within 24 Hours