In a contract for three more units how many labor hours


Jack Simpson, contract negotiator for Nebula Airframe Company, is currently involved in bidding on a follow-up government contract. In gathering cost data from the first three units, which Nebula produced under a research and development contract, he found that the first unit took 2,000 labor hours, the second took 1,400 labor hours, and the third took 1,320 hours. Use Exhibit 6.5.

In a contract for three more units, how many labor hours should Simpson plan for? (Round your answer to the nearest whole number.)

Request for Solution File

Ask an Expert for Answer!!
Operation Management: In a contract for three more units how many labor hours
Reference No:- TGS02486115

Expected delivery within 24 Hours