In a certain standard costing system the following results


In a certain standard costing system the following results occurred last period: labor rate variance, $1,000 U; labor efficiency variance, $2,800 F; and the actual labor rate was $0.20 more per hour than the standard labor rate. The number of actual direct labor-hours used last period was: