In 2016 the westgate construction company entered into a


In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2018. Information related to the contract is as follows:

            2016 2017 2018

Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800

Estimated costs to complete as of year-end 5,256,000 2,628,000 0

Billings during the year 2,170,000 2,502,000 5,328,000

Cash collections during the year 1,885,000 2,600,000 5,515,000

Westgate recognizes revenue over time according to percentage of completion.

Required: 1. Calculate the amount of revenue and gross profit to be recognized in each of the three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.) Calculate the amount of revenue and gross profit to be recognized in each of the three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.)

2-a. In the journal below, complete the necessary journal entries for the year 2016 (credit "Various accounts" for construction costs incurred). (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.) 2-b. In the journal below, complete the necessary journal entries for the year 2017 (credit "Various accounts" for construction costs incurred). (If no entry is required for a transaction/event, select "No journal entry required" in the first

Request for Solution File

Ask an Expert for Answer!!
Financial Accounting: In 2016 the westgate construction company entered into a
Reference No:- TGS01689626

Expected delivery within 24 Hours