If there is a penalty of 5000 a week for each week the


The project described in the following table has just begun. It is scheduled to be completed in 12 weeks.

UseTable B1andTable B2.

Activity Estimated Time
(weeks) Standard
Deviation (wks.)
1-2 4 0.78
2-4 4 0.88
1-3 5 0.51
3-4 9 1.95

a. If you were the manager of this project, would you be concerned?(Round "Probability" valuesto 4 decimal places, intermediate calculations and final answers to 2 decimal places.)

(Click to select)Yes No because the probability of finishing on schedule is only about.

b.  If there is a penalty of $5,000 a week for each week the project is late, what is the probability of incurring a penalty of at least $5,000?(Round "Probability" valuesto 4 decimal places, intermediate calculations and final answers to 2 decimal places.)

Request for Solution File

Ask an Expert for Answer!!
Mathematics: If there is a penalty of 5000 a week for each week the
Reference No:- TGS01251452

Expected delivery within 24 Hours