If the overall cost factor for the complete system is 245


The equipment for applying specialty coatings that provide a high angle of skid for the paper- board and corrugated box industries has a delivered cost of $390,000. If the overall cost factor for the complete system is 2.45, the total plant cost is approximately:

a. $955,500

b. $1,054,400

c. $1,154,400

d. $1,544,400

Please show all work