If the first unit of production requires 1200 hours and the


1. If the first unit of production requires 1,200 hours and the 150th unit requires 315 hours, then what learning curve is the company performing at?

2. A company has decided to bid on a follow-on contract for 500 units of a product. The company has already produced 2,000 units on a 75 percent learning curve. The 2000th unit requires 80 hours of production time. If a fully burdened hour is $80 and the company wishes to generate a 12 percent profit, how much should be bid?